Free template

Testable requirements checklist

Turn "the product should be good" into requirements a team can build to and a test can pass or fail.

Download PDFPrint this pageAll templates

Testable requirements checklist

Check every requirement against this

Weak to testable (example numbers: set your own)

WeakTestable
Battery should last a long time.At least 8 h of the standard use profile at 25 °C, measured from 100% to shutdown.
Must be rugged.Survives 10 drops from 1.2 m onto concrete with no loss of function.
Easy to assemble.Assembled in under 90 s by a trained operator with no tools beyond the fixture.
Runs cool.Case surface stays below 45 °C after 2 h at full load in a 30 °C room.

The four-week set-up

WeekOutputDone?
1 · PRDWhat the product must do and for whom, every line testable. Review with someone who will build it.
2 · TRDTechnical limits and interfaces, each with an owner. Interface specs signed by both sides.
3 · Critical pathTask list with dependencies. The longest chain marked. Lab and tooling lead times included.
4 · KickoffPlan with contingency written in. Risks listed. Gate criteria agreed in advance.

Why: a requirement nobody can test is a debate waiting to happen at the gate. Contingency is not padding; it is the honest admission that something unplanned will happen.

From The Hardest Hardware Lessons · thehardesthardwarelessons.com · Free to use and share with attribution.

One hardware lesson a week, free

Short, blunt lessons from the book: the mistake, what it costs, what to do instead. No spam, unsubscribe any time.

Want the reasoning behind every line?

The book explains each phase, each gate and the mistakes these checklists are built to catch.

Get the book →Play the games