← → to navigate · F for fullscreen
Slide 1 of 6 · The hook

Have you ever worked really hard on something — only to find out it was wrong when it was too late to fix cheaply?

That feeling has a name in hardware. It's called discovering your mistake at the wrong phase. And the cost is not 2x. It's not 10x. It's closer to 100x.

1 / 6
Slide 2 of 6 · The 100x rule

The same mistake costs 100x more to fix in production than in prototyping.

Prototyping €1,000s Board re-spin, a week of delay. Painful but manageable.
After tooling €50k – €100k Tooling modification. 6–8 weeks. No schedule buffer.
Mass production €100k – €1M+ Line halt. Cert re-test. Potential field recall.
In the field Existential Recall + press coverage + customer trust. Companies don't recover.
2 / 6
Slide 3 of 6 · DFM & specification

The most expensive mistakes are decided before the first prototype is built.

Design for Manufacturability means specifying your product with the factory in mind from day one — not as a late-stage review.

Spec

Tolerances set too tight in CAD — looks fine on screen, requires specialised tooling in production. Cost discovered at DVT: €40k re-work.

Spec

Component chosen for prototype availability — impossible to source at volume. Single-source risk locked in before anyone noticed.

DFM

Assembly sequence not reviewed with the factory — requires manual intervention on 40% of units. Invisible on a bench. Catastrophic at 10,000 units per week.

DFM

Thermal not simulated before hard tooling — the €80,000 tooling modification that nobody planned for.

3 / 6
Slide 4 of 6 · The real villain

It's not incompetence.
It's not bad engineering.
It's pressure.

"The team passes the DVT gate with two open hardware issues that are 'probably fine.' They don't take the two-week extension. Six weeks later, in PVT, those two issues cost five times as much to resolve — in a phase where the schedule has no buffer, because the schedule was set assuming DVT would close on time."

— The Hardest Hardware Lessons
4 / 6
Slide 5 of 6 · The lesson
"Every shortcut you take today is a cost you pay downstream — at a higher rate, under worse conditions."

On specification

Every deferred decision costs more to fix. Specify completely and involve manufacturing before money is committed.

On DFM

DFM is not a review at the end of design. It's a discipline from the first sketch. The factory should be in the room before tooling is discussed.

On gate discipline

Hold the gate when evidence doesn't support moving forward. That two-week extension is not failure — it's the most economically rational decision you can make.

On pressure

Separate "we feel behind" from "we are genuinely ready." Those are different questions with very different answers.

5 / 6
Slide 6 of 6 · The close

I wrote all of this down.
45 copies sold in 6 days.
Hardware people recognising something true.

The book

The Hardest Hardware Lessons

thehardesthardwarelessons.com/buy

Weekly lessons — free to follow

The Hardest Hardware Lessons on Substack

thehardesthardwarelessons.substack.com

6 / 6